Here welist onlya selection of ourwide range ofreferences.
2016
Most important references in 2016
Client: NSW Cable laying with own cable laying barge „NOSTAG 10“ at OWP Nordergründe. PLGR, general assistance and anchor handling with our FlatTop Tug “Torsten”.
Client: Enercon Transport of wind turbine parts with own tug and pontoon.
Client: Elos Spedition Transport of a portal crane within port of Bremen with own tug and pontoon.
Client: Martens en Van Oord (Subcontractor to ARGE Neubau 5. Schleusenkammer Brunsbüttel) Transport of excavated soil from Brunsbuettel (construction of the new lock chamber) to Dyhrrsenmoor.
Client: Matthäi Wasserbau Handling of barges in Lübeck.
Client: ARGE Neubau 5. Schleusenkammer Brunsbüttel Transport of vehicles and personnel from shore to site within the scope of the new building of the 5th lock chamber in Brunsbüttel
Client: Deme Group / GeoSea Provision of an assistance tug as well as runner crew for 46 calls of Kiel-Canal (Elbe p/s – Kiel LH and vice versa)
2015
Most important references in 2015
Project: Onshore WP components
Transport of 3x E-70/4 WEC and 3x Steel Tower E-70 with a barge and two tugs from Emden and Malmö to Föhr. Stability, load out / load in, vessel coordination, custom clearance. Client: Enercon
Project: KFE / BorWin 3/ DolWin 3
Cable laying with own cable laying barge „NOSTAG 10“ at OWP KFE, Borwin 3 and Dolwin 3. Assistance and anchor handling with our multicat “TORSTEN”. Client: Bohlen & Doyen
2014
Most important references in 2014
Project: OWP Nordsee Ost Transport of 48 x 6M nacelles and hubs with a barge and tugboat from Bremerhaven LH to Bremerhaven CT1. Design of seafastening, cribbing, stability, load out / load in, vessel coordination, custom clearance Client: Senvion
Project: Onshore WP Dagebüll Transport of 4 x 6.2M wind turbines (hub, nacelles, lower and upper tower sections) with a barge and two tugs from Cuxhaven and Bremerhaven to Dagebüll. Design of seafastening, cribbing, stability, load out / load in, vessel coordination, custom clearance Client: Senvion
2013
Most important references in 2013
July: OWP “West of Duddon Sands” / Irish Sea Working as assistance for cable laying barge “STEMAT 89” and “STEMAT SPIRIT” , e.g. anchor handling, transfers Client: Stemat / VSMC
June: DolWin Alpha / BorWin Alpha ROV-Survey at DolWin Alpha / BorWin Alpha platforms, measurements with a multibeam echosounder Client: Vermessungsbüro Weigt
May-June: Assistance EIDERBARGE 42 für Transportlogistik-Projekt "Thornton Bank III" Assistance at River Weser and River Elbe, as well as harbor assistance at the port of Bremerhaven and Cuxhaven. Client: REpower Systems SE
May: Towage EIDERBARGE 42 Towage of “EIDEBARGE 45” from Kiel / Germany to Hoydalsbygd / Norway. Client: Nobiskrug GmbH
Serveral assistances at the Kiel-Canal Working as assistance tug at the Kiel-Canal and on the river Elbe/ Kiel Fjord, e.g. tug “JADE” with pontoon “STRALSUND”
January-March: Deconstruction of platform “Manslagt Z1” Deconstruction of the gas platform “Manslagt Z1” with jack up barge “ODIN”. Towage and positioning of jack up barge “ODIN”, transport of equipment and crew transfer, anchor handling, towage of working pontoons. Client: HOCHTIEF Solutions AG / Exxon Mobil
Cable connection Offshore Windpark Borkum West 2 Assistance and anchorhandling with two tugs (TORSTEN & MAX) for cable laying with NOSTAG 10
August till November: OWP “Borkum West II” Working as assistance for cable laying barge “NOSTAG 10” at OWP “Borkum West 2”, e.g. anchor handling Client: NSW – Norddeutsche Seekabelwerke GmbH
May till July: OWP "Baltic 2" Working as assistance for cable laying barge “NOSTAG 10” at OWP “Baltic 2”, e.g. initiation of ROV-trencher, anchor handling. Client: NSW – Norddeutsche Seekabelwerke GmbH
April: Tug TORSTEN Commissioning at Sanmar Shipyard/ Turkey; mobilization to Brunsbüttel.
2011
Most important references in 2011
Cable connection Wales - Irland Laying ofcablesbetween Walesand Irelandwitha total lengthof 36.5km withthecable-layingbargeNOSTAG 10andthetugs MAX andMORITZ Client: EireGrid/ABB
2nd part OWP Rödsand 2, Baltic Sea The internal wiring Park was carried out with our cable-laying barge NOSTAG 10. We were responsible for the provision of cable applicant, the marine crew, the tug and for navigational advice Client: E.ON
Further references
Further significant references
2009 Cable connection Helgoland, Northsea The cable laying work for the network connection of the island of Helgoland was carried out with our cable ship NOSTAG10 with a total cable length of 53 km to St. Peter-Ording. We were responsible for the provision of cable applicant, the marine crew, the tug and for navigational advice. Client: E.ON
2008 Landing of a second submarine cable for Norderney based on a „Zero introductory concept“ Conversion of standard barges to noiseless cable ferries Cooperation: Hans Schramm, NavConsult Client: TAGU Tiefbau Unterweser
2008 Revision of an underwater research facility Under observance to the traffic on the Baltic Sea Construction of a platform with four-point mooring system, accommodation for the team, decompression chamber, diving entry point. Client: Public authorities
2008 Offshore Cable Norddeich/Norderney, Northsea The cable-laying took place in the Wadden Sea area 1 and was carried out with our own tractors and P1 pontoon. We were responsible for the warm-up of the pontoons and beaching of the pontoons. This outstanding maritime skills for tidal waters and tightest maneuvers of the crews of the tugs were required. The implementation of non-motor-driven water transport has been developed in advance by us, designed and installed by us on site. In addition, we were responsible for maritime consultancy. Client: NSW – Norddeutsche Seekabel Werke
2005/2006 Pipeline building Mittelplate A, Northsea In this project we have equipped the renovation and equipping of 12 catamaran pontoons to units for drilling and to some extent with our own tugs between Brunsbüttel, Cuxhaven and the offshore location abducted position and ballasted. Client: RWE-Dea AG/Wintershall
1996-2006Mittelplate A, Northsea Year-round transportation of wet oil by means of two tank barges from the „Mittelplate A“ in the German Bight to Brunsbüttel Oilport. Client: RWE-Dea AG